Oakland Avenue Bulb-Outs and Nova/Magnolia Traffic Island Improvements
Summary: This project installed traffic safety improvements at the Oakland/Jerome, Oakland/El Cerrito, and Nova/Magnolia intersections.
Status: Completed
Documents:
Updates:
- October 4, 2021: The City Council directs staff to proceed with the design of traffic safety improvements at the Oakland/Jerome and Oakland/El Cerrito intersections.
- November 1, 2022: Neighborhood meeting to discuss preliminary concepts.
- March 6, 2023: The City Council reviewed the proposed improvements and directed staff to proceed with the preparation of construction documents.
- November 6, 2023: The City Council awarded the construction agreement to Terocons, Inc.